TL;DR: A commercial security bid should move in a fixed order: read the specifications, complete the device and cable takeoff, secure current material pricing, build labor from measured units and job conditions, add project overhead and risk, then price the work to your margin target. Markup and margin aren’t interchangeable. A 30% markup on cost produces only a 23.1% margin on the selling price.
Moving from residential or light commercial into larger commercial work changes the bid more than the install. The devices are familiar. The specs, schedules, wage rules and closeout requirements are where a bid that looked profitable turns into a job that isn’t.
Why should you read the spec before you count anything?
Read the spec first because it tells you what you’re allowed to install, what you have to submit and what you’ll be held to at closeout, and none of that shows up on the drawings.
On projects organized under the Construction Specifications Institute’s MasterFormat, electronic safety and security work is commonly placed in Division 28 (Electronic Safety and Security), while communications cabling is commonly placed in Division 27 (Communications). The complete scope may also depend on Division 01 general requirements and Division 08 door hardware. Follow the issued project manual rather than assuming the division number defines every obligation.
As you read, mark these:
- Basis of design and approved equals. Is the spec closed to one manufacturer, or does it allow equals? Is there a substitution request process, and when does it close?
- Submittal requirements. Shop drawings, data sheets and battery and voltage drop calculations. Note how many rounds of review to expect.
- Testing, commissioning and training. Who has to witness what, how many hours of owner training and whether a third party is involved.
- Closeout documents. As-builts, O&M manuals, warranty letters and programming backups.
- Wage and labor requirements. Prevailing wage, certified payroll, union requirements or owner-specific badging and escort rules.
- Warranty terms. One year is common, but some specs ask for more.
Every one of those items costs labor hours. If you don’t find them in the spec, you won’t price them, and you’ll still have to do them.
If the spec names a product you can’t get or don’t want to install, read our post on how to substitute a spec’d product without losing the bid before bid day.
How do you do a takeoff for devices and cable?
A good takeoff counts every device from the drawings, measures every cable run with slack and routing included and gets checked twice before it becomes a material list.
Start with devices. Work floor by floor and system by system, and mark each device on the drawings as you count it so you don’t double count or skip one. Compare your counts with any device schedule in the drawings or specs. When the schedule and the drawings disagree, note it and send a question to the engineer before bid day.
Then cable. Measure each run along the path the cable will actually take, not a straight line. Add:
- Vertical distance up to the ceiling and down to the device.
- Routing around obstacles, like structural members, fire walls and other trades’ work.
- Slack at both ends for terminations and service loops.
- Waste, because some cable always ends up on the floor.
Some estimators add a flat percentage for waste and slack. Others add a fixed length per drop. Either works if you’re consistent and you track it against what your crews actually use. The number to avoid is the one you made up on the last bid and never checked.
Before you price anything, check the takeoff a second time, ideally with fresh eyes or a second person. A missed floor or a door hardware schedule you didn’t see is the kind of error that’s free to catch before the bid and expensive to catch after.
How do you get accurate material pricing before bid day?
Send your distributor a complete project quote request well before bid day, with drawings, spec sections, device counts, cable footage, approved equals and your timeline in one package.
Material pricing is the part of the bid you shouldn’t have to guess. Your distributor can price the job to your quantities and tell you what’s in stock and what has a lead time, but only if they have enough information to work with. A request that says “need pricing on 60 cameras” will get a number. A request with the drawings and the spec section will get a number you can bid with.
Ask for alternates when the spec allows approved equals, priced separately and clearly labeled, so you can choose at bid time. Ask how long the pricing holds, because a bid that sits for 60 days before award can see material costs change.
Two other things to settle before bid day:
- Open your account if you haven’t. A credit review shouldn’t hold up your first order after award. See how to open a wholesale account with a security distributor.
- Price the whole job in one place if you can. When fire, access control, video and cable all come from one distributor, it’s easier to check that the pieces work together. Our post on why the best contractors buy across categories from one distributor covers why.
Our companion post on requesting a project quote lists exactly what to send and what to ask.
How do you estimate labor hours for a low-voltage job?
Estimate labor by assigning a labor unit (hours per device or per foot of cable) to every item in your takeoff, then adjusting for jobsite conditions and adding the hours that don’t attach to any one device.
Labor units are the base. Many contractors build their own from completed jobs. Others start from published references like the NECA Manual of Labor Units and adjust from there. Your own historical data beats any published number, because it reflects your crews, your methods and your market.
Then adjust for conditions. The same camera mount takes different hours depending on where it goes:
- Ceiling height. Work above 12 to 14 feet often means a lift, which means rental cost, setup time and slower work.
- Ceiling type. Hard lid, open structure and drop ceiling each take a different amount of time to work through.
- Occupied buildings. Working around tenants, patients or students often means restricted hours, escorts and daily cleanup.
- Access and parking. Badging, security screening and long walks from the truck add time every day.
- Wage requirements. If the contract is covered by Davis-Bacon or another prevailing wage rule, use the applicable classifications, wage determination, fringe benefits and payroll requirements when you build labor cost.
- Schedule. Phased work, night shifts and compressed schedules all cost hours.
Then add the labor people forget, because it doesn’t attach to a device on the drawings:
- Programming and configuration for panels, cameras, access controllers and VMS.
- Testing and commissioning, including witnessed tests and retests.
- Owner training.
- Submittals and closeout documents, including as-builts and O&M manuals.
- Project management, meetings and coordination with other trades.
Price these as separate line items. They’re real hours, and on a commercial job they can add up to a meaningful share of the total.
What is the difference between markup and margin?
Markup is profit as a percentage of your cost. Margin is profit as a percentage of your selling price. The same dollar amount of profit always produces a smaller margin percentage than markup percentage.
That difference matters because overhead and profit targets are usually set as a share of revenue, which is margin. If you set your price by adding a markup percentage to cost and think of it as margin, you’ll come in under your target every time.
Here’s an illustration. Assume a job with $80,000 in total direct cost (material, labor and job-specific expenses).
| Pricing approach | Selling price | Gross profit | Markup on cost | Margin on price |
|---|---|---|---|---|
| Add 30% markup to cost | $104,000 | $24,000 | 30.0% | 23.1% |
| Price for a 30% margin | $114,286 | $34,286 | 42.9% | 30.0% |
The contractor who meant to bid a 30 percent margin and added 30 percent to cost left $10,286 on the table on this one job.
The formulas:
- Price from markup: Price = Cost x (1 + markup)
- Price from margin: Price = Cost / (1 – margin)
- Convert markup to margin: Margin = markup / (1 + markup)
- Convert margin to markup: Markup = margin / (1 – margin)
These numbers are illustrations, not a recommended margin. The right target depends on your overhead, your market and the risk on the job. What matters is knowing which number you’re using and doing the math the same way on every bid.
What overhead, permit and risk costs belong in a security bid?
A complete bid covers the costs that don’t show up in the takeoff: permits and inspections, warranty, general overhead and a contingency for the risk on the job.
Go through these on every bid:
- Permits and inspection fees. Fire alarm permits, low-voltage permits and re-inspection fees vary by jurisdiction. Check the local fee schedule.
- Plan review and engineering. Some jurisdictions require stamped fire alarm drawings, and some specs require a licensed designer on submittals.
- Bonds and insurance. Performance and payment bonds, plus any additional insured or coverage requirements in the contract.
- Equipment and rentals. Lifts, trenching equipment, test gear and storage containers.
- Warranty labor. Every callback during the warranty period costs a truck roll. Price the warranty the spec actually asks for.
- Retainage. Many commercial contracts hold back a percentage of each payment until closeout. That’s not a cost on paper, but it ties up cash you’ll need to carry.
- General overhead. Your office, vehicles, insurance, software and the people who don’t bill to the job.
- Contingency. A line for what you can’t see yet: unclear drawings, a tight schedule, an unfamiliar GC or a building with old infrastructure.
Contingency is a judgment call. A clean set of drawings on a new build with a GC you’ve worked with before carries less risk than a retrofit in an occupied hospital. Price the difference.
What should be on a bid review checklist before you submit?
Before you submit, run a final pass that checks the scope, the math and the assumptions, ideally with someone who didn’t build the estimate.
- Every spec section in your scope is accounted for, including testing, training and closeout.
- Device counts match the drawings and the schedules, and every discrepancy has an RFI or a stated assumption.
- Cable footage includes vertical runs, routing, slack and waste.
- Material pricing is current, covers every line in the takeoff and holds through the expected award date.
- Alternates are priced and labeled if the spec allows equals.
- Labor reflects jobsite conditions, wage requirements and schedule.
- Programming, commissioning and closeout are separate line items.
- Permits, bonds, rentals and warranty are included.
- Price is set on margin, and the math has been checked.
- Exclusions and clarifications are written down and included with the bid.
That last item protects you. If you excluded patching and painting, conduit by others or 120 VAC power to your panels, say so in writing. Clear exclusions prevent arguments after award.
Where does Security Data Supply fit in the bid?
Security Data Supply supports the material side of the bid: project pricing, alternates for approved equals, product knowledge and availability from a locally owned franchise in your market.
Security Data Supply doesn’t install or bid jobs. What a franchise can do is price your material to your quantities and timeline, help you find alternates when the spec allows equals, pull data sheets and listing documents for submittals and tell you what’s in stock before you commit to a schedule. Project pricing and availability are handled case by case, and special project pricing may need manufacturer approval. Because Security Data Supply franchises carry fire alarm, intrusion, video surveillance, access control, AV, networking, wire and cable, power and tools, a job that crosses categories can be priced in one place.
System design, code compliance and the bid itself stay with you. Getting the material number right is one less thing to worry about on bid day.
Winning more commercial work is also how many contractors start adding service and monitoring revenue. Our post on how security contractors build recurring monthly revenue covers where to start. See how security contractors expand revenue streams for where that tends to lead, and how to choose a wholesale security distributor if you’re still deciding who to buy from.
Have a commercial job going out to bid? Send the drawings and spec sections to your local SDS franchise for project pricing.
Frequently asked questions
How do I bid a commercial security installation?
Work through the bid in order: read the spec, do a device and cable takeoff, get material pricing from your distributor, build labor from per-device units adjusted for jobsite conditions, add overhead, permits and contingency, and set the price using margin. Finish with a review pass and written exclusions before you submit.
How do I estimate labor hours for a low-voltage job?
Assign a labor unit to every device and cable run in the takeoff, using your own historical data or a published reference like the NECA Manual of Labor Units as a starting point. Adjust for ceiling height, occupied buildings, access, wage requirements and schedule. Then add separate hours for programming, testing, commissioning, training and closeout.
What is the difference between markup and margin?
Markup is profit as a percentage of cost. Margin is profit as a percentage of selling price. A 30 percent markup on $80,000 in cost produces a $104,000 price and a 23.1 percent margin. To earn a 30 percent margin on the same cost, the price has to be about $114,286, which is a 42.9 percent markup.
What does Division 28 cover in a construction spec?
In CSI MasterFormat, Division 28 (Electronic Safety and Security) commonly covers access control, intrusion detection, video surveillance and fire detection and alarm. Communications cabling is commonly placed in Division 27. Follow the issued project manual, and check Division 01 for general requirements and Division 08 for door hardware tied to access control.
What costs do contractors forget to include in a security bid?
The most commonly missed costs are programming and configuration, testing and commissioning, owner training, closeout documents, lift rentals, permits and inspection fees, warranty callbacks and the labor impact of occupied buildings or prevailing wage requirements.
Should I include programming, commissioning and closeout as line items?
Yes. Programming, commissioning, training and closeout documents are real labor hours that don’t attach to any one device on the drawings. Listing them separately makes sure they’re priced and makes it clear to the GC or owner what the bid includes.
How do I get accurate material pricing before bid day?
Send your distributor one complete project quote request with drawings, spec sections, device counts, cable footage, approved equals, the bid date and your delivery timeline. Ask how long the pricing holds and request alternates priced separately when the spec allows equals.
About the author
Ron Broussard is Chief Executive Officer of Security Data Supply and has more than 30 years of experience in the security industry. He has held executive leadership roles across distribution and manufacturing, giving him a broad perspective on the challenges contractors, integrators and distributors face every day. At Security Data Supply, he guides the company’s franchise network, vendor relationships and long-term growth strategy.
Methodology
This article describes a general approach to estimating commercial security, fire and low-voltage work based on common industry practice and the experience of Security Data Supply franchise teams. Dollar figures and percentages are illustrations of the math, not recommended margins, markups or labor units. Bidding requirements vary by project, contract and jurisdiction.
Sources and further reading
- Construction Specifications Institute: MasterFormat
- U.S. Department of Labor: Davis-Bacon and Related Acts
- NECA: Manual of Labor Units
- How to Request a Project Quote From a Security Distributor
- How Security Contractors Build Recurring Monthly Revenue (RMR)
- How Security Contractors Expand Revenue Streams
- How to Substitute a Spec’d Product Without Losing the Bid
- Why the Best Contractors Buy Across Categories From One Distributor
- How to Choose a Wholesale Security Distributor
- How to Open a Wholesale Account With a Security Distributor